Classesand counts

Each machine gets a class from its production impact (1 to 3) times how often its parts fail (1 to 3): 6 or 9 is A (critical), 3 or 4 is B, 1 or 2 is C. A spare takes the class of the most critical machine it is fitted on.

Labelled bins in rows
Class = impact × failure frequency
Production impactLess than once a year (1)About once a year (2)Several times a year (3)
Little or none (1)C (1)C (2)B (3)
Part of the line (2)C (2)B (4)A (6)
Line or plant stops (3)B (3)A (6)A (9)

Reorder point = use per business day × (your lead-time estimate + the safety days of the class), rounded. The safety days are 20 for A, 10 for B and 0 for C; change them in Settings. The shelf uses the larger of this point and your minimum.

Example: 12 bearings a year over about 245 business days is 0,05 a day; with 5 business days of lead time and 20 safety days for class A, that is about 1,2, so the point is 1. With a minimum of 2, the spare is reordered at 2.

A spare at or below its point, counting what is already on order, goes to the basket with a suggestion back to the maximum.

Counts: class A every 30 days, B every 90, C every 180. A count sets the stock; the difference from the last figure shows what was used or lost.

Starting values (change them in the app's Settings)
ClassSafety daysCount every
A20 business days30 days
B10 business days90 days
C0 business days180 days

Open the reorder calculator